Supply Chain Tracker

Material procurement, vendor performance & price tracking

Total Value

$100.1M

Orders

20

In Transit

2

Critical In-Progress

3

Material Orders

Showing 20 of 20
IDMaterialSupplierAmountOrder DateExpected DeliveryStatus PipelineCritical
MO-001

Structural steel (floors 1-14)

Delivered 2 days early

Nucor Steel$8.5MSep 15, 2025Apr 20, 2026Actual: Apr 18, 2026
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
MO-002

Structural steel (floors 15-28)

Fabrication at 60%; on schedule

Nucor Steel$7.2MJan 10, 2026Sep 1, 20266 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
MO-003

Structural steel (floors 29-42)

Shop drawings approved

Nucor Steel$6.8MApr 1, 2026Nov 15, 202681 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
MO-004

Rebar (foundation)

Mill certs verified

Commercial Metals Co$2.8MNov 1, 2025Feb 15, 2026Actual: Feb 15, 2026
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
MO-005

Rebar (superstructure)

Rolling shipments monthly

Commercial Metals Co$3.4MFeb 1, 2026Aug 20, 2026
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-006

Concrete (ready-mix contract)

On-call delivery; 4,000+ CY poured to date

Boston Sand & Gravel$12.4MOct 15, 2025Jan 5, 2026Actual: Jan 5, 2026
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
MO-007

Curtain wall system

Mock-up testing in September; fabrication 35% complete

Permasteelisa Group$17.2MDec 1, 2025Nov 1, 202667 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
MO-008

Elevators (8 passenger + 2 freight)

Manufacturing on track; monthly progress reports

Otis Elevator$8.2MAug 1, 2025Jan 15, 2027142 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-009

Metal decking

Rolling delivery matching steel erection pace

Vulcraft$4.6MJan 15, 2026May 10, 2026Actual: May 12, 2026
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-010

HVAC equipment (chillers, AHUs)

Long-lead items; 18-week fabrication cycle

Trane Technologies$6.8MMar 15, 2026Jan 20, 2027147 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-011

Electrical switchgear

Submittals under review

Eaton Corporation$3.2MApr 1, 2026Dec 15, 2026111 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-012

Fire suppression piping

Design coordination ongoing

Viking Group$2.4MMay 1, 2026Feb 1, 2027159 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-013

Generator sets (emergency)

2x 2MW diesel generators

Caterpillar$2.1MMar 1, 2026Nov 1, 202667 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-014

Waterproofing membrane

Applied and inspected

Carlisle Companies$1.8MJan 10, 2026Mar 15, 2026Actual: Mar 14, 2026
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-015

Tower crane

Operational since Jan 15; 280-ton capacity

Liebherr$1.5MJul 15, 2025Jan 10, 2026Actual: Jan 8, 2026
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
MO-016

Plumbing fixtures (bulk)

Spec confirmed; order placed

Kohler Co$1.4MJun 1, 2026Mar 1, 2027187 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-017

Fire alarm system

Design phase; submittal pending

Honeywell$2.2MMay 15, 2026Jan 15, 2027142 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-018

Façade stone cladding

Quarry selection finalized; sample approved

Polycor$2.8MApr 15, 2026Feb 1, 2027159 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-
MO-019

Concrete formwork system

Self-climbing formwork for core; operational

PERI Group$3.2MOct 1, 2025Feb 1, 2026Actual: Feb 1, 2026
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
MO-020

Interior glass partitions

Design development stage

Dormakaba$1.6MJul 1, 2026Jun 1, 2027279 days away
Ordered
Fabricating
Shipping
Delivered
Installing
Complete
-

Vendor Performance Scorecards

Nucor Steel

3 orders · $22.5M

On-Time Delivery95%
Quality
4.5
Communication
4.0

Permasteelisa Group

1 order · $17.2M

On-Time Delivery88%
Quality
4.0
Communication
3.5

Boston Sand & Gravel

1 order · $12.4M

On-Time Delivery98%
Quality
4.5
Communication
5.0

Otis Elevator

1 order · $8.2M

On-Time Delivery90%
Quality
5.0
Communication
4.0

Trane Technologies

1 order · $6.8M

On-Time Delivery85%
Quality
4.5
Communication
3.5

Commercial Metals Co

2 orders · $6.2M

On-Time Delivery92%
Quality
4.0
Communication
3.5

Vulcraft

1 order · $4.6M

On-Time Delivery91%
Quality
4.0
Communication
4.0

Eaton Corporation

1 order · $3.2M

On-Time Delivery88%
Quality
4.0
Communication
4.0

PERI Group

1 order · $3.2M

On-Time Delivery96%
Quality
5.0
Communication
5.0

Polycor

1 order · $2.8M

On-Time Delivery87%
Quality
4.5
Communication
3.5

Viking Group

1 order · $2.4M

On-Time Delivery93%
Quality
4.0
Communication
4.0

Honeywell

1 order · $2.2M

On-Time Delivery92%
Quality
4.5
Communication
4.0

Caterpillar

1 order · $2.1M

On-Time Delivery90%
Quality
5.0
Communication
4.5

Carlisle Companies

1 order · $1.8M

On-Time Delivery96%
Quality
4.5
Communication
4.0

Dormakaba

1 order · $1.6M

On-Time Delivery89%
Quality
4.0
Communication
4.0

Liebherr

1 order · $1.5M

On-Time Delivery97%
Quality
5.0
Communication
5.0

Kohler Co

1 order · $1.4M

On-Time Delivery90%
Quality
4.0
Communication
3.5

Lead Time VisualizationCritical path materials — order to expected delivery

Ordered
Fabricating
Shipping
Delivered
Installing
Complete

Material Price IndexIndexed to 100 (Jan 2026 baseline)

steel

114

-1 vs prev month

concrete

107

+1 vs prev month

lumber

102

-2 vs prev month

copper

115

+3 vs prev month

Critical Path Materials8 materials on critical path

MO-001complete

Structural steel (floors 1-14)

Nucor Steel

$8.5M

217-day lead time

Ordered
Fabricating
Shipping
Delivered
Installing
Complete

Ordered

Sep 15, 2025

Expected

Apr 20, 2026

Actual

Apr 18, 2026

On-Time:95%
Quality:4.5/5
Comm:4/5

Delivered 2 days early

MO-002fabricating

Structural steel (floors 15-28)

Nucor Steel

$7.2M

234-day lead time

Ordered
Fabricating
Shipping
Delivered
Installing
Complete

Ordered

Jan 10, 2026

Expected

Sep 1, 2026

Days Until

6 days

On-Time:95%
Quality:4.5/5
Comm:4/5

Fabrication at 60%; on schedule

MO-003ordered

Structural steel (floors 29-42)

Nucor Steel

$6.8M

228-day lead time

Ordered
Fabricating
Shipping
Delivered
Installing
Complete

Ordered

Apr 1, 2026

Expected

Nov 15, 2026

Days Until

81 days

On-Time:95%
Quality:4.5/5
Comm:4/5

Shop drawings approved

MO-004complete

Rebar (foundation)

Commercial Metals Co

$2.8M

106-day lead time

Ordered
Fabricating
Shipping
Delivered
Installing
Complete

Ordered

Nov 1, 2025

Expected

Feb 15, 2026

Actual

Feb 15, 2026

On-Time:92%
Quality:4/5
Comm:3.5/5

Mill certs verified

MO-006installing

Concrete (ready-mix contract)

Boston Sand & Gravel

$12.4M

82-day lead time

Ordered
Fabricating
Shipping
Delivered
Installing
Complete

Ordered

Oct 15, 2025

Expected

Jan 5, 2026

Actual

Jan 5, 2026

On-Time:98%
Quality:4.5/5
Comm:5/5

On-call delivery; 4,000+ CY poured to date

MO-007fabricating

Curtain wall system

Permasteelisa Group

$17.2M

335-day lead time

Ordered
Fabricating
Shipping
Delivered
Installing
Complete

Ordered

Dec 1, 2025

Expected

Nov 1, 2026

Days Until

67 days

On-Time:88%
Quality:4/5
Comm:3.5/5

Mock-up testing in September; fabrication 35% complete

MO-015installing

Tower crane

Liebherr

$1.5M

179-day lead time

Ordered
Fabricating
Shipping
Delivered
Installing
Complete

Ordered

Jul 15, 2025

Expected

Jan 10, 2026

Actual

Jan 8, 2026

On-Time:97%
Quality:5/5
Comm:5/5

Operational since Jan 15; 280-ton capacity

MO-019installing

Concrete formwork system

PERI Group

$3.2M

123-day lead time

Ordered
Fabricating
Shipping
Delivered
Installing
Complete

Ordered

Oct 1, 2025

Expected

Feb 1, 2026

Actual

Feb 1, 2026

On-Time:96%
Quality:5/5
Comm:5/5

Self-climbing formwork for core; operational