Meridian Tower
42-story mixed-use commercial/industrial building · Boston, MA · Month 8 of 36
Project Budget
$215.0M
22% timeline elapsed · Structural phase
Active Alerts
Steel Fabrication Tracking
Floors 15-28 steel fabrication at 60%. Lead time projecting 1-week buffer remaining.
Weekend Weather Advisory
Thunderstorms forecast Sunday — crane operations will be suspended. Plan indoor activities.
Workforce Below Plan
Current workforce 485 vs. planned 510 (-4.9%). Ironworker availability contributing factor.
Change Order Volume
12 change orders totaling $3.85M (1.8% of contract). Approaching monitoring threshold.
Schedule
-5 days
behind schedule
Budget Variance
+4.8%
$2.8M over
RFIs / Submittals
34 / 18
active / open
Safety (TRIR)
1.2
23 days since last
Workforce
485
of 510 planned
Change Orders
$3.9M
12 total