Meridian Tower

42-story mixed-use commercial/industrial building · Boston, MA · Month 8 of 36

Project Budget

$215.0M

78Health

22% timeline elapsed · Structural phase

Active Alerts

Steel Fabrication Tracking

Floors 15-28 steel fabrication at 60%. Lead time projecting 1-week buffer remaining.

Weekend Weather Advisory

Thunderstorms forecast Sunday — crane operations will be suspended. Plan indoor activities.

Workforce Below Plan

Current workforce 485 vs. planned 510 (-4.9%). Ironworker availability contributing factor.

Change Order Volume

12 change orders totaling $3.85M (1.8% of contract). Approaching monitoring threshold.

Schedule

-5 days

behind schedule

Trending to recover

Budget Variance

+4.8%

$2.8M over

CPI: 0.85

RFIs / Submittals

34 / 18

active / open

Safety (TRIR)

1.2

23 days since last

Below industry avg

Workforce

485

of 510 planned

Change Orders

$3.9M

12 total

Budget: Planned vs Actual vs Earned Value ($M)

7-Day Weather Forecast

WedSunny82°/66°No impact
ThuPartly Cloudy85°/69°No impact
FriScattered Showers79°/64°minor
SatRain74°/60°moderate
SunThunderstorms72°/58°severe
MonPartly Cloudy76°/62°No impact
TueSunny80°/65°No impact

Phase Progress

Pre-Construction
100%
Foundation
100%
Structure
42%
Envelope
0%
MEP
1%
Interiors
0%
Commissioning
0%

Key Milestones

Foundation completeMay 2026complete
Structure topped outDec 2026upcoming
Envelope closedJun 2027upcoming
MEP rough-in completeOct 2027upcoming
Substantial completionSep 2028upcoming
Final completionDec 2028upcoming

Earned Value Performance (CPI & SPI)