Schedule & Timeline
Meridian Tower · 36-month construction schedule · Month 8
Today: Aug 26, 2026 · Day 233 of 1078
Complete
11
of 41 activities
In Progress
5
actively underway
At Risk / Delayed
0
require attention
Critical Path
20
activities on critical path
Filter by Phase
Gantt Chart
Jan 2026 - Dec 2028 · Horizontal bars show activity duration and progress
Complete
In Progress
Upcoming
At Risk
Delayed
Milestone
Critical Path
Today
Q2 2026
Q3 2026
Q4 2026
Q1 2027
Q2 2027
Q3 2027
Q4 2027
Q1 2028
Q2 2028
Q3 2028
Q4 2028
Pre-Construction
Site mobilization
Jan 5 - Jan 23100%
100%
Demolition & site clearing
Jan 12 - Feb 6100%
100%
Environmental remediation
Jan 19 - Feb 20100%
100%
Foundation
Excavation & shoring
Feb 9 - Mar 20100%
100%
Dewatering system
Feb 16 - Apr 10100%
100%
Pile driving (deep foundations)
Mar 2 - Apr 17100%
100%
Foundation concrete (mat slab)
Mar 23 - May 1100%
100%
Foundation waterproofing
Apr 13 - May 8100%
100%
Foundation complete
May 8100%
Structure
Structural steel erection (floors 1-14)
May 4 - Jul 17100%
100%
Metal decking (floors 1-14)
May 18 - Jul 31100%
100%
Concrete on metal deck (floors 1-14)
Jun 1 - Aug 1485%
85%
Structural steel erection (floors 15-28)
Jul 20 - Oct 230%
30%
Metal decking (floors 15-28)
Aug 3 - Oct 1610%
10%
Concrete on metal deck (floors 15-28)
Aug 17 - Oct 300%
0%
Structural steel erection (floors 29-42)
Oct 5 - Dec 180%
0%
Core concrete (elevator & stair shafts)
May 11 - Nov 2055%
55%
Structure topped out
Dec 180%
Envelope
Curtain wall installation (lower)
Sep 7 - Jan 160%
0%
Curtain wall installation (upper)
Jan 4 - Jun 130%
0%
Roofing system
Mar 1 - Apr 250%
0%
Envelope closed
Jun 130%
MEP
MEP rough-in (lower floors)
Sep 21 - Mar 125%
5%
MEP rough-in (upper floors)
Mar 15 - Oct 80%
0%
Elevator installation
Jan 4 - Sep 240%
0%
Fire suppression systems
Feb 1 - Aug 220%
0%
Building automation system
Jun 2 - Nov 210%
0%
MEP rough-in complete
Oct 80%
Interiors
Drywall & framing (lower)
Apr 5 - Aug 150%
0%
Drywall & framing (upper)
Oct 11 - Feb 280%
0%
Flooring installation
Sep 6 - Apr 150%
0%
Ceiling systems
Oct 4 - Mar 220%
0%
Painting & finishes
Jan 3 - Jun 170%
0%
Specialty items & fixtures
Mar 7 - Jul 180%
0%
Commissioning
MEP commissioning
Apr 3 - Aug 90%
0%
Life safety testing
Jun 5 - Aug 220%
0%
Elevator inspections & certification
Jul 11 - Sep 60%
0%
Punch list & remediation
Jul 5 - Sep 250%
0%
Substantial completion
Sep 250%
Owner move-in & closeout
Oct 1 - Dec 180%
0%
Final completion
Dec 180%
Today (Aug 26)
Milestone Tracker
Foundation complete
May 8, 2026Foundation
Critical Path
Complete
Completed on May 8, 2026
Structure topped out
Dec 18, 2026Structure
Critical Path
Upcoming
114 days remaining
0%
Envelope closed
Jun 13, 2027Envelope
Critical Path
Upcoming
291 days remaining
0%
MEP rough-in complete
Oct 8, 2027MEP
Critical Path
Upcoming
408 days remaining
0%
Substantial completion
Sep 25, 2028Commissioning
Critical Path
Upcoming
761 days remaining
0%
Final completion
Dec 18, 2028Commissioning
Critical Path
Upcoming
845 days remaining
0%