Financial Calculator & Cost Management

Meridian Tower — $215M Budget · Month 8 of 36

Cost Breakdown Structure

DivCategory / DescriptionBudgetedCommittedSpentForecastVariance
01
General Requirements(4)
$28.4M$28.3M$10.5M$28.9M$-450K
02
Existing Conditions(2)
$4.3M$4.3M$4.2M$4.3M+$50K
03
Concrete(3)
$32.9M$30.8M$15.3M$34.0M$-1.1M
04
Masonry(1)
$3.1M$2.9M$0$3.1M$0
05
Metals(3)
$29.2M$28.3M$10.4M$30.1M$-900K
07
Thermal & Moisture(3)
$24.3M$20.4M$800K$24.5M$-200K
08
Openings(1)
$3.2M$0$0$3.2M$0
09
Finishes(4)
$14.5M$0$0$14.5M$0
10
Specialties(2)
$1.4M$0$0$1.4M$0
14
Conveying(1)
$8.5M$8.2M$1.2M$8.5M$0
21
Fire Suppression(1)
$4.8M$4.4M$0$4.8M$0
22
Plumbing(1)
$6.2M$5.8M$400K$6.2M$0
23
HVAC(2)
$17.7M$16.8M$800K$18.0M$-300K
26
Electrical(3)
$19.6M$14.3M$1.6M$19.8M$-200K
27
Communications(1)
$3.8M$0$0$3.8M$0
28
Electronic Safety(2)
$4.2M$2.2M$0$4.2M$0
31
Earthwork(2)
$6.8M$6.8M$6.5M$6.8M$0
32
Exterior Improvements(1)
$1.8M$0$0$1.8M$0
SC
Soft Costs(6)
$29.9M$21.1M$14.1M$30.1M$-200K
Grand Total$244.7M$194.5M$65.7M$247.9M$-3.3M

Change Order Manager

Approved: $3.4M (10)Pending/Negotiating: $465K (2)
IDTitleCategoryStatusDateCost ImpactSchedule (days)Phase
CO-001Foundation underpinning modificationUnforeseen conditionsapproved2026-03-12+$420K+5Foundation
CO-002Structural steel connection upgradeDesign changeapproved2026-04-18+$285K--Structure
CO-003Added generator capacityOwner requestapproved2026-03-01+$680K--MEP
CO-004Concrete mix design optimizationSchedule accelerationapproved2026-02-10+$165K-7Structure
CO-005Waterproofing system upgradeCode complianceapproved2026-04-05+$125K+3Foundation
CO-006MEP coordination reroutingDesign coordinationapproved2026-07-20+$210K--MEP
CO-007Enhanced lobby finish upgradeOwner requestapproved2026-05-15+$850K--Interiors
CO-008Additional site security measuresSafety/securityapproved2026-02-20+$145K--All
CO-009Curtain wall gasket material changeDesign changeapproved2026-06-10+$320K--Envelope
CO-010Electrical panel relocationOwner requestnegotiating2026-08-01+$275K+7MEP
CO-011Stormwater retention tank upsizingCode complianceapproved2026-03-20+$185K--Foundation
CO-012Additional structural reinforcement at floor 22Owner requestpending2026-08-15+$190K+3Structure

Cash Flow — Cumulative Planned vs Actual ($M)

Earned Value Management

CPI (Cost Performance)0.92
SPI (Schedule Performance)0.97
EAC (Estimate at Completion)$232.9M
ETC (Estimate to Complete)$171.7M
VAC (Variance at Completion)$-17.9M
Over budget projection
Cumulative Planned Value

$58.4M

Cumulative Actual Cost

$61.2M

Cumulative Earned Value

$56.5M

Technology ROI Calculator

Inputs

Results

Total Projected Savings

$206K

$1,700 / week x 28 months

Return on Investment

+37.4%

Net gain: $56K

Payback Period

20.4 months

Within project timeline